existing electric installations

Safety checks of existing installations are commonly referred to as ‘periodic inspection and testing’ and an electrical installation condition report (EICR) is completed and issued.

 

Safety checks of existing installations are commonly referred to as ‘periodic inspection and testing’ and an electrical installation condition report (EICR) is completed and issued.

If anything dangerous or potentially dangerous is found, the overall condition of the electrical installation will be declared to be ‘unsatisfactory’. In this situation we can advise you on what remedial action is required.

Recommended frequency of inspection ranges from 6 months to 10 years depending on the type of installation. For example, rented accommodation is every change of occupancy and 5 years. 

The table below provides guidance on the initial frequency of formal inspections of electrical installations and routine checks.

PAT Testing can also be carried out alongside an EICR. Get in touch for a quote for testing of your property or multiple units. 

Click on our review page to see what our customers are saying.

 

General Installation 

 

Type of Installation Routine Check Maximum Period between Inspections and testing as necessary
Domestic accommodation – general Change of occupancy /10 years
Domestic accommodation – rented houses and flats 1 year Change of occupancy /5 years
Residential (Houses of Multiple Occupation)- halls of residence, nurses accomodation, etc 1 year Change of occupancy /5 years
Commercial 1 Year Change of occupancy /5 years
Educational Establishments 6 Months 5 years
Industrial 1 Year 3 years
Offices 1 Year 5 years
Shops 1 Year 5 years
Laboratories 1 Year 5 years

 

 

 

 

 

 

 

Hospitals and medical clinics 

 

Type of Installation Routine Check Maximum Period between Inspections and testing as necessary
Hospitals and medical clinics general area 1 Year 5 years
Hospitals and medical clinics medical locations 6 months 1 year

 

 

 

 

 

 

 

Buildings Open to the Public 

 

Type of Installation Routine Check Maximum Period between Inspections and testing as necessary
Cinemas 1 Year 1 to 3 years
Church Installations 1 Year 5 Years
Leisure complexes (ex swimming pool) 1 Year 3 years
Places of public entertainment 1 Year 3 years
Restaurants/hotels 1 Year 5 years
Theatres 1 Year 3 years
Public Houses 1 Year 5 years
Village halls / Community Centres 1 Year 5 years

 

 

 

 

 

 

 

Special and Specific Installations (for medical locations see above) 

 

Type of Installation Routine Check Maximum Period between Inspections and testing as necessary
Agricultural 1 Year 3 Years
Caravans 1 Year 3 Years
Caravan Parks 6 Months 1 Year
Highway power supplies as convenient 6-8 years
Marinas 4 months 1 Year
Fish Farms 4 months 1 Year
Swimming Pools 4 months 1 Year
Emergency Lighting Daily/Monthly 3 Years
Fire Alarms Daily/Weekly 1 Year
Launderettes monthly 1 Year
Petrol Filling 1 Year 1 Year
Construction Site Installations 3 Months 3 Months